Power infrastructure
- The proposed Hatch–Wadley 500 kV transmission line is proposed to cross the property for approximately one mile.
- Existing 115 kV and 230 kV transmission lines approximately 1.26 miles and 2.8 miles to the east, respectively.
- 115 kV substation approximately three miles north of the property.
- 10 miles south of the Wadley; Georgia Power substations, control center, east–west 500 kV transmission line and the proposed Hatch–Wadley line endpoint.
- Approximately 60 miles north of Plant Hatch nuclear power station and surrounding substations.
- Several solar plants in the surrounding area.